Project Performance Evaluation using EVA Technique: Kotay Bridge Construction Project on Kayto River in Afghanistan


Creative Commons License

UĞURAL M. N., BURGAN H. İ.

TEHNICKI VJESNIK-TECHNICAL GAZETTE, cilt.28, sa.1, ss.340-345, 2021 (SCI-Expanded) identifier identifier

  • Yayın Türü: Makale / Tam Makale
  • Cilt numarası: 28 Sayı: 1
  • Basım Tarihi: 2021
  • Doi Numarası: 10.17559/tv-20200114133619
  • Dergi Adı: TEHNICKI VJESNIK-TECHNICAL GAZETTE
  • Derginin Tarandığı İndeksler: Science Citation Index Expanded (SCI-EXPANDED), Scopus, Aerospace Database, Communication Abstracts, Compendex, INSPEC, Metadex, Directory of Open Access Journals, Civil Engineering Abstracts
  • Sayfa Sayıları: ss.340-345
  • Anahtar Kelimeler: bridge project, Earned Value Analysis (EVA), kotay bridge, project performance evaluation, river
  • Akdeniz Üniversitesi Adresli: Evet

Özet

The objective of the study is the assessment of an operating bridge project in terms of its performance by the evaluate project performance (EVA) technique. To apply the EVA technique, cost and schedule baselines and an update record of performed work with spent money is prepared for the project. The data is taken directly from site office of the project. Kotay bridge construction project is selected for case study. Project tracking is achieved by taking EVA technique to assess the Kotay bridge construction project performance in the last five months, and to find out the cost and time overruns if they exist. The Estimation at Completion (EAC) and To-Complete Performance Index (TCPI) are found as well to know how efficiently are used the remaining financial resources. The study revealed that CPI and SPI are both less than 1.0, which means that the project could not be performed well. Cost & time overruns are clearly indicated as well.